Crossing on Main Road near Erick Avenue

 

 

You will notice that some of the work has been done on the pedestrian crossing, but the work is still incomplete; there is a stretch of concrete that made the anticipated cabling connection impossible and a new trench was required for the pre-requisite cable duct. As an interim measure, the standard beacon and crank pole have been fitted while they await delivery of both the halo beacons and the non-standard longer crank poles which will project the beacons further into the drivers eye line than they are at present.

 

.